Concrete Slab Calculator
Estimate how much concrete a rectangular slab needs: this concrete slab calculator turns length, width and thickness into cubic yards, cubic meters and the number of 80, 60 or 40 lb bags, with an optional waste allowance for spillage and an uneven base. For the price of the pour, use the concrete slab cost calculator with your own local prices.
Result
| Volume | |
| Volume (metric) | |
| Order quantity (with waste) | |
| Bags of premix (with waste) |
Units & conversions used
Imperial inputs are feet and inches; results are shown in cubic feet, cubic yards (1 yd³ = 27 ft³) and cubic meters (1 ft³ = 0.02832 m³). Metric inputs are converted first: 1 m = 3.28084 ft, 1 cm = 0.3937 in.
Formula & source
V(yd³) = V(ft³) ÷ 27
Source: basic rectangular-prism geometry. The 5–10% waste allowance is standard ready-mix ordering practice (covers spillage, form deflection and subgrade unevenness); it is an industry rule of thumb, not a code requirement. Structural design (rebar, thickness for loads) is governed by ACI 318 and local codes — this calculator does not cover that.
Worked example (you can verify by hand)
Input: 10 ft × 12 ft slab, 4 in thick, 7% waste.
- Thickness in feet: 4 ÷ 12 = 0.3333 ft
- Volume: 10 × 12 × 0.3333 = 40.00 ft³
- Cubic yards: 40 ÷ 27 = 1.4815 yd³
- With 7% waste: 1.4815 × 1.07 = 1.5852 yd³
Expected output: 1.48 yd³ (1.59 yd³ with waste), 1.13 m³ (1.21 m³ with waste).
Limitations — what this cannot do
- This estimates volume only. It does not design slab thickness, reinforcement, joint spacing or subgrade preparation — those follow ACI 318 and local building codes; consult a structural engineer for load-bearing slabs.
- Assumes a perfectly rectangular slab of uniform thickness. Irregular shapes need to be broken into rectangles (or use our column/footing calculators for those parts).
- Ready-mix suppliers have minimum load charges; small orders may cost more per yard.
Does a "4-inch" slab on 2×4 forms really take 4 inches of concrete?
No: a slab screeded flush with 2×4 forms is 3.5 in deep at the edges, so it needs 12.5% less concrete than the 4 in figure, while every extra ¼ in of average depth from a low subgrade adds 6.3% to a 4 in slab. We ran this page's own slab function over common sizes to put numbers on both effects.
Method (2026-10-19): we called Calcs.concreteSlab(length, width, thickness, 0) from this page's calcs.js in Node for each case, with no waste added. Dressed lumber depths are the dry minimum-dressed sizes in NIST PS 20-25 American Softwood Lumber Standard, Table 3 (2×4 = 3-1/2 in, 2×6 = 5-1/2 in, 2×8 = 7-1/4 in). Bag counts use 0.60 ft³ per 80 lb bag, rounded up. Raw results: concrete-slab-form-depth-test.json.
| Slab | Form board | Depth | yd³ at nominal | yd³ at dressed | Difference | 80 lb bags |
|---|---|---|---|---|---|---|
| 10x10 ft | 2x4 | 4 in → 3.5 in | 1.24 | 1.08 | 0.15 (12.5%) | 56 → 49 |
| 10x10 ft | 2x6 | 6 in → 5.5 in | 1.85 | 1.70 | 0.15 (8.3%) | 84 → 77 |
| 10x12 ft | 2x4 | 4 in → 3.5 in | 1.48 | 1.30 | 0.18 (12.5%) | 67 → 59 |
| 10x12 ft | 2x6 | 6 in → 5.5 in | 2.22 | 2.04 | 0.18 (8.3%) | 100 → 92 |
| 12x12 ft | 2x4 | 4 in → 3.5 in | 1.78 | 1.56 | 0.22 (12.5%) | 80 → 70 |
| 12x12 ft | 2x6 | 6 in → 5.5 in | 2.67 | 2.44 | 0.22 (8.3%) | 120 → 110 |
| 12x12 ft | 2x8 | 8 in → 7.25 in | 3.56 | 3.22 | 0.33 (9.4%) | 160 → 145 |
| 16x16 ft | 2x4 | 4 in → 3.5 in | 3.16 | 2.77 | 0.40 (12.5%) | 143 → 125 |
| 16x16 ft | 2x6 | 6 in → 5.5 in | 4.74 | 4.35 | 0.40 (8.3%) | 214 → 196 |
| 20x20 ft | 2x4 | 4 in → 3.5 in | 4.94 | 4.32 | 0.62 (12.5%) | 223 → 195 |
| 20x20 ft | 2x6 | 6 in → 5.5 in | 7.41 | 6.79 | 0.62 (8.3%) | 334 → 306 |
| 20x20 ft | 2x8 | 8 in → 7.25 in | 9.88 | 8.95 | 0.93 (9.4%) | 445 → 403 |
| 24x24 ft | 2x4 | 4 in → 3.5 in | 7.11 | 6.22 | 0.89 (12.5%) | 320 → 280 |
| 24x24 ft | 2x6 | 6 in → 5.5 in | 10.67 | 9.78 | 0.89 (8.3%) | 480 → 440 |
| Slab | Design depth | Average extra depth | yd³ needed | Extra vs design | Covered by 10% waste? |
|---|---|---|---|---|---|
| 10x10 ft | 4 in | +0.25 in | 1.31 | +0.08 (+6.3%) | yes |
| 10x10 ft | 4 in | +0.5 in | 1.39 | +0.15 (+12.5%) | no |
| 10x10 ft | 4 in | +1 in | 1.54 | +0.31 (+25%) | no |
| 10x10 ft | 6 in | +0.25 in | 1.93 | +0.08 (+4.2%) | yes |
| 10x10 ft | 6 in | +0.5 in | 2.01 | +0.15 (+8.3%) | yes |
| 10x10 ft | 6 in | +1 in | 2.16 | +0.31 (+16.7%) | no |
| 12x12 ft | 4 in | +0.25 in | 1.89 | +0.11 (+6.3%) | yes |
| 12x12 ft | 4 in | +0.5 in | 2.00 | +0.22 (+12.5%) | no |
| 12x12 ft | 4 in | +1 in | 2.22 | +0.44 (+25%) | no |
| 12x12 ft | 6 in | +0.25 in | 2.78 | +0.11 (+4.2%) | yes |
| 12x12 ft | 6 in | +0.5 in | 2.89 | +0.22 (+8.3%) | yes |
| 12x12 ft | 6 in | +1 in | 3.11 | +0.44 (+16.7%) | no |
| 20x20 ft | 4 in | +0.25 in | 5.25 | +0.31 (+6.3%) | yes |
| 20x20 ft | 4 in | +0.5 in | 5.56 | +0.62 (+12.5%) | no |
| 20x20 ft | 4 in | +1 in | 6.17 | +1.24 (+25%) | no |
| 20x20 ft | 6 in | +0.25 in | 7.72 | +0.31 (+4.2%) | yes |
| 20x20 ft | 6 in | +0.5 in | 8.03 | +0.62 (+8.3%) | yes |
| 20x20 ft | 6 in | +1 in | 8.64 | +1.24 (+16.7%) | no |
| 24x24 ft | 4 in | +0.25 in | 7.56 | +0.44 (+6.3%) | yes |
| 24x24 ft | 4 in | +0.5 in | 8.00 | +0.89 (+12.5%) | no |
| 24x24 ft | 4 in | +1 in | 8.89 | +1.78 (+25%) | no |
| 24x24 ft | 6 in | +0.25 in | 11.11 | +0.44 (+4.2%) | yes |
| 24x24 ft | 6 in | +0.5 in | 11.56 | +0.89 (+8.3%) | yes |
| 24x24 ft | 6 in | +1 in | 12.44 | +1.78 (+16.7%) | no |
What the tables show: the 2×4 gap is the same 12.5% at every slab size (a 2×6 gives 8.3%, a 2×8 9.4%), so measure the real depth you will pour, not the lumber name. A 10% waste allowance covers ¼ in of extra average depth on any slab and ½ in on a 6 in slab, but not ½ in on a 4 in slab (+12.5%) or a full inch anywhere (+16.7% to +25%). Check the base with a string line before you order; the concrete base calculator sizes the gravel layer under the slab. Limits: the subgrade rows assume a uniform extra depth; real low spots are patchy, so take several depth readings and average them.
FAQ
How many cubic yards of concrete do I need for a 10×12 slab at 4 inches?
40 ft³ ÷ 27 = 1.48 yd³ before waste. Order about 1.6 yd³ with a 7% allowance. Most suppliers round up to the nearest quarter or half yard.
Should I add extra for waste?
Yes — 5–10% is standard practice. Forms flex, subgrade is never perfectly level, and some concrete sticks to the chute and wheelbarrow. It is cheaper than a short load and a cold joint.
How thick should my concrete slab be?
This calculator cannot answer that — thickness depends on loads and soil. As a rough reference, 4 in is common for patios and walkways, 5–6 in for residential driveways, but confirm with local code or an engineer.
How do I convert cubic feet to cubic yards?
Divide by 27. One cubic yard = 27 cubic feet (3 ft × 3 ft × 3 ft).
How much does it cost to pour a concrete slab?
A concrete slab's material cost is its volume times your local price, so start from the cubic yards above: each $100 per cubic yard of ready-mix costs $1.235 per square foot of a 4-inch slab before waste ($1.852 at 6 inches), and one cubic yard in bags is 45 bags of 80 lb mix at your shelf price. We do not quote a national average because bag prices, ready-mix quotes and short-load fees differ by store and supplier; the concrete slab cost calculator compares bags with a ready-mix truck using the prices you enter. Installed contractor quotes also include base preparation, forms, reinforcement, finishing and labor.
How long does concrete take to cure?
Concrete is moist-cured for at least 7 days (3 days for high-early-strength mixes, ACI 301) and reaches its specified strength at the 28-day test age (ACI 318), at normal temperatures around 73°F; colder concrete takes longer.
| Milestone | Published time at normal temperature | Source |
|---|---|---|
| Foot traffic (bagged mix) | 24 hours (Sakrete High-Strength, Maximizer); 12 hours (Sakrete 5000 Plus) | Sakrete technical data sheets |
| Cars on a parking-lot slab | 3 days; all other traffic 7 days | ACI 330R, via FHWA-RD-02-099 |
| Keep the slab moist | At least 7 days (3 for high-early mixes) | ACI 301, via FHWA-RD-02-099 |
| Specified strength | 28 days | ACI 318 test age |
To see how many calendar days those milestones take at your temperatures, use the concrete curing time calculator; for pours near freezing see cold weather concrete pouring.
For floor preparation over an existing slab, use the self leveling concrete calculator to estimate underlayment bags from fill depth.