Concrete Footing Calculator
Size continuous strip footings or isolated pad/pier footings in cubic yards and bags, with optional $/yd³, a stated rebar takeoff from length × width, and a US frost-depth helper that can override the depth input. Volume and shopping-list math only — not structural design.
Quick answer
A 30 ft × 16 in × 8 in continuous strip footing needs 0.99 yd³ exact (26.67 ft³), or 1.04 yd³ with 5% waste — about 47 × 80 lb bags (0.60 ft³ yield). Default rebar takeoff for that run: ~51 lb of #4 (2 continuous bars + transverses @ 18 in o.c., 3 in cover). Four 2×2 ft × 12 in pads at 7% waste need 0.63 yd³ (~29 × 80 lb). Frost: IRC floor is 12 in; local Table R301.2 frost line may be deeper — use the helper below, then confirm with your building department.
Last updated 2026-11-03 · Uses Calcs.concreteFooting, Calcs.footingRebar, Calcs.frostDepthForState. Bag yields match Quikrete Concrete Mix No. 1101 (Oct 2022 sheet). Method note: rebar and frost helpers are stated takeoff/planning models, not industry design standards.
How much concrete for my footing?
Result
| Mode | |
| Volume (exact) | |
| Volume (metric) | |
| Order quantity (with waste) | |
| 80 lb bags (0.60 ft³) | |
| 60 lb bags (0.45 ft³) | |
| 40 lb bags (0.30 ft³) | |
| Optional cost | |
| Bag vs ready-mix tip | |
| Rebar takeoff | |
| Rebar assumption |
Frost-depth helper (US) — planning override
IRC R403.1.4 requires exterior footings at least 12 inches below undisturbed ground. IRC R403.1.4.1 requires frost protection by extending below the local frost line, using a frost-protected shallow foundation (R403.3 / ASCE 32), or bearing on solid rock. The frost-line value itself is filled by the jurisdiction in Table R301.2 — local code wins. This helper suggests a planning depth you can push into the depth field; it is not a substitute for your building department.
Frost suggestion
| Suggested planning depth | |
| Source kind | |
| Note | |
| IRC floor (R403.1.4) | 12 in below undisturbed ground |
code_published = named statewide/amended residential figure we cite; planning_mid = mid-range estimate for volume planning only. Always verify Table R301.2 locally.
How to use this concrete footings calculator
- Choose Continuous strip or Isolated pad / pier.
- Enter length, width and depth (imperial or metric). In pad mode, enter how many pads.
- Optional: set waste %, ready-mix $/yd³, rebar size and spacing.
- Optional: pick a US state in the frost helper and apply the suggested depth before calculating.
- Read yd³ to order, 80/60/40 lb bag counts, optional cost, bag-vs-truck tip, and rebar takeoff pounds.
Units, formula & sources
Pad: V(ft³) = count × L(ft) × W(in)/12 × D(in)/12
V(yd³) = V(ft³) ÷ 27 · bags = ceil( V(ft³)×(1+waste%) ÷ bag_yield )
Sources: rectangular-prism geometry; Quikrete Concrete Mix No. 1101 data sheet (revised Oct 2022) for 80/60/40 lb yields (0.60 / 0.45 / 0.30 ft³); ASTM A615 nominal bar weights (#3 0.376, #4 0.668, #5 1.043 lb/ft); IRC R403.1.4 / R403.1.4.1 / Table R301.2 for frost-protection rules (jurisdiction fills the frost-line number). Cover default 3 in references ACI 318 concrete cast against earth as a cut-length assumption only.
Worked example — strip footing you can verify by hand
Input: continuous strip 30 ft × 16 in × 8 in, 5% waste, #4 @ 18 in o.c., 3 in cover.
- Width ft: 16÷12 = 1.3333; depth ft: 8÷12 = 0.6667
- Volume: 30 × 1.3333 × 0.6667 = 26.67 ft³ → 0.9877 yd³
- With 5% waste: 1.037 yd³ · 80 lb bags: ceil(26.67×1.05 / 0.60) = 47
- Rebar: 2 × 30 ft = 60 ft longitudinal; transverses ceil(360/18)=20 × (16−6)/12 = 16.67 ft; total 76.67 ft × 0.668 ≈ 51.2 lb
Expected tool output: 1.04 yd³ to order, 47 / 63 / 94 bags (80/60/40), ~51 lb #4 takeoff.
Strip vs pad — same page dual-mode comparison
Cells from Calcs.concreteFooting and Calcs.footingRebar on this site. Strip rebar uses 18 in transverse spacing; pad grid uses 12 in o.c. each way; both #4 with 3 in cover.
| Job | Mode | yd³ w/ waste | 80 lb bags | Rebar lb (#4) | Bag/truck tip |
|---|---|---|---|---|---|
| 30 ft × 16×8 in, 5% | Strip | 1.037 | 47 | 51.2 | Compare both (~1 yd³) |
| 40 ft × 20×10 in, 10% | Strip | 2.263 | 102 | 74.5 | Compare both |
| 20 ft × 12×8 in, 5% | Strip | 0.519 | 24 | 31.4 | Bags often practical |
| 60 ft × 16×8 in, 7% | Strip | 2.114 | 96 | 102.4 | Compare both |
| 4 pads × 2×2 ft × 12 in, 7% | Pad | 0.634 | 29 | 24.0 | Bags often practical |
| 6 pads × 3×2.5 ft × 12 in, 10% | Pad | 1.833 | 83 | 62.1 | Compare both |
| 8 pads × 2×2 ft × 10 in, 5% | Pad | 1.037 | 47 | 48.1 | Compare both |
Rebar estimator assumptions (honest limits)
- Strip: 2 continuous longitudinal bars of the chosen size along the full length, plus transverse bars of the same size cut to (width − 2×cover) and spaced at your spacing (default 18 in).
- Pad / pier: rectangular grid of the chosen size at your spacing (default 12 in when you switch mode) each way; multiplied by pad count.
- Not included: dowels into walls/columns, hooks, lap splices, stirrup shapes, grade beams, seismic special detailing, or soil-bearing checks.
- Not a design: IRC/ACI minimum reinforcement, bar size, and spacing for your loads and seismic category come from the approved plan or a licensed engineer. This block is a shopping-list takeoff from stated geometry only.
Bag vs ready-mix truck — threshold tip
After volume-with-waste is known, this page labels a budgeting tip (not a price quote):
- < 1 yd³ — bagged mix is often practical for DIY (labor and mixing time still count).
- 1–3 yd³ — compare both; ready-mix short-load fees can erase the per-yard advantage.
- > 3 yd³ — a truck usually wins on labor and consistency for footings.
Local bag retail, truck minimums, and access (wheelbarrow distance) decide the real cutoff. Optional $/yd³ on the tool only multiplies your typed rate × yards with waste.
Reading concrete footings cost on this page
On this page, concrete footings cost is the optional ready-mix line: the $/yd³ rate you type × the order quantity (yd³ with waste) in the result table. That product is what the Optional cost row means — concrete only, not digging, forms, rebar purchase, pump, tax, or short-load fees. Leave $/yd³ blank when you only need volume and bags; fill it when you want a planning concrete footings cost against a supplier’s delivered rate.
Worked strip check: 1.04 yd³ to order × $180/yd³ → about $187 as the concrete-only concrete footings cost here. Swap in your local delivered $/yd³; the tool multiplies that rate by the same yards-with-waste figure it already shows for bags and truck tips.
Frost helper — sample state suggestions
Examples from Calcs.frostDepthForState. Use the live dropdown for all states. Local Table R301.2 overrides every row.
| State | Suggested in | Kind | Note (short) |
|---|---|---|---|
| FL | 12 | code_published | Frost NA; IRC 12 in minimum |
| CT | 42 | code_published | CT SBC Table R301.2 statewide 42 in |
| MA | 48 | code_published | 780 CMR Table R301.2 — 48 in |
| MI | 42 | code_published | MRC R403.1.4 — 42 in below grade |
| MN | 42 | code_published | Zones 42 or 60 in — helper uses 42 (south) |
| NJ | 36 | code_published | 30 in south / 36 in north — helper uses 36 |
| WI | 48 | code_published | SPS 321.16 floor 48 in |
| TX | 12 | planning_mid | Most areas frost-light; Panhandle deeper |
| CO | 36 | planning_mid | Denver-area examples ~36 in; mountains deeper |
Limitations — what this cannot do
- Estimates volume, bags, optional cost, and a stated rebar takeoff only. It does not design footing width, depth, concrete strength, or reinforcement for loads or frost heave.
- Assumes rectangular prisms of uniform section. Stepped footings need section-by-section sums. Round cardboard forms: use the sonotube concrete calculator.
- Frost suggestions do not replace the jurisdiction’s Table R301.2 value or an engineered FPSF design.
- Trenches are rarely perfect — hand-dug trenches may need more than the waste you enter.
Frost-line depth × soil bearing → minimum strip width (editable assumptions)
The frost helper on this page answers a depth planning question. Soil bearing answers a separate width planning question. Neither number designs the footing. The table below multiplies a typed line load (plf) by an editable allowable bearing (psf) with the shopping-list identity min_width_ft = line_load_plf ÷ bearing_psf, then converts to inches. Frost depth is shown only so both planning dimensions sit on one card — frost does not change the width algebra.
Honesty: the 1,500 / 2,000 / 3,000 psf columns are editable planning assumptions you type, not national averages, not a soil report, and not IRC Table R401.4.1. Local code, an engineer, or a soils report can floor the width above these cells (many jurisdictions will not accept a strip thinner than about 12 in under a load-bearing wall even when the algebra is smaller). Replace every assumption before digging.
| Planning frost depth (in) | Typed line load (plf) | @ 1,500 psf assume | @ 2,000 psf assume | @ 3,000 psf assume | Width note |
|---|---|---|---|---|---|
| 12 (FL / many frost-light zones) | 1,500 | 12.0 in | 9.0 in | 6.0 in | 9 in and 6 in are algebra only — expect a local minimum to raise them |
| 36 (NJ north helper / CO mid) | 2,000 | 16.0 in | 12.0 in | 8.0 in | 16 in matches this page’s strip seed width at the softest assume |
| 42 (CT / MI / MN-south helpers) | 2,500 | 20.0 in | 15.0 in | 10.0 in | Depth 42 in ≠ wider strip; width still follows plf÷psf |
| 48 (MA / WI helpers) | 3,000 | 24.0 in | 18.0 in | 12.0 in | Heavier wall load, not deeper frost, drives the 24 in cell |
Worked check: 2,000 plf ÷ 2,000 psf = 1.00 ft = 12 in. Same load on a 1,500 psf assumption is 1.333 ft = 16 in — the strip seed already on this calculator. Changing frost from 12 in to 48 in does not move that width; it only changes the depth you may push into the depth field. Feed the chosen width and depth into Calcs.concreteFooting for yards and bags; do not treat this table as structural design.
Pad count from wall length ÷ max span + edge offset
Pad mode on this calculator asks “how many pads?” It does not invent that count from a wall length. This block does: place the first and last pad centers an editable edge offset e in from each end, then space interiors so center-to-center never exceeds an editable max span S.
actual_cc = (L − 2e) / (n_pads − 1)
Honesty: S and e are planning knobs you type (examples below use e = 1.5 ft or 2 ft and S = 8 ft or 10 ft). They are not beam design, not joist span tables, and not a claim that the soil or the grade beam can carry that spacing. After you have n_pads, size each pad in pad mode and multiply volume by the count.
| Wall length L (ft) | Edge offset e (ft) | Max span S (ft) | n_pads | Actual c–c (ft) | Check |
|---|---|---|---|---|---|
| 24 | 1.5 | 8 | 4 | 7.00 | ≤ 8 ✓ |
| 30 | 1.5 | 8 | 5 | 6.75 | ≤ 8 ✓ |
| 40 | 1.5 | 8 | 6 | 7.40 | ≤ 8 ✓ |
| 40 | 2.0 | 10 | 5 | 9.00 | ≤ 10 ✓ |
| 48 | 1.5 | 8 | 7 | 7.50 | ≤ 8 ✓ |
| 60 | 2.0 | 10 | 7 | 9.33 | ≤ 10 ✓ |
Worked 40 ft / e = 1.5 / S = 8: (40 − 3) ÷ 8 = 4.625 → ceil 5 → 6 pads, actual spacing 37 ÷ 5 = 7.40 ft. Enter count = 6 in pad mode with your pad L×W×D to get combined yards. Round cardboard piers still belong on the sonotube calculator — this count math is for rectangular pads only.
Column load ÷ soil bearing → pad area and square side
For one isolated pad under a posted load, the planning identity is A_ft² = P_lb ÷ q_psf, then for a square pad side_ft = √A. Round the side up to the next 0.25 ft for a constructability seed, then enter that side (as length and width) plus thickness into pad mode.
Honesty: P and q are editable assumptions. P is the service load you type (dead + live as your plan states), not a measured reaction from this site. q is not a national soil average. Eccentric loads, overturning, punching shear, and reinforcement are out of scope — the rebar block already states soil-bearing checks are not included.
| Column load P (lb) | q assume (psf) | Area A (ft²) | Exact side (ft) | Round-up side (ft) | Enter in pad mode (in × in) |
|---|---|---|---|---|---|
| 8,000 | 2,000 | 4.00 | 2.00 | 2.00 | 24 × 24 |
| 12,000 | 2,000 | 6.00 | 2.45 | 2.50 | 30 × 30 |
| 20,000 | 2,000 | 10.00 | 3.16 | 3.25 | 39 × 39 |
| 20,000 | 1,500 | 13.33 | 3.65 | 3.75 | 45 × 45 |
| 30,000 | 2,000 | 15.00 | 3.87 | 4.00 | 48 × 48 |
| 40,000 | 3,000 | 13.33 | 3.65 | 3.75 | 45 × 45 |
Worked check: 20,000 lb ÷ 2,000 psf = 10 ft² → √10 = 3.162 ft → round up to 3.25 ft (39 in). Four such pads at 12 in thick with 7% waste is the same geometry family as the page’s “4 pads × 2×2 ft × 12 in” seed, only larger in plan — run pad mode for yards and bags rather than scaling the seed by eye. If the post is round and uses a cardboard form, leave this page and use the sonotube calculator for the shaft volume.
FAQ
How many cubic yards of concrete do I need for a 30-foot footing that is 16 inches wide and 8 inches deep?
30 × (16 ÷ 12) × (8 ÷ 12) = 26.67 ft³ ÷ 27 = 0.99 yd³. With 5% waste order about 1.04 yd³ (47 × 80 lb bags at 0.60 ft³ yield).
What is the formula for footing concrete volume?
Strip: V(ft³) = length_ft × (width_in ÷ 12) × (depth_in ÷ 12), then yd³ = ft³ ÷ 27. Pad/pier mode multiplies that prism by the pad count.
How do I estimate rebar for a concrete footing?
This page's takeoff is not a structural design. Strip default: 2 continuous #4 bars plus #4 transverses at 18 in o.c. with 3 in cover. Pad default: #4 grid at 12 in o.c. each way. Your approved plan or engineer governs real steel.
How deep should a footing be for frost?
IRC R403.1.4 requires exterior footings at least 12 in below undisturbed ground; R403.1.4.1 adds frost protection below the local frost line (or FPSF / solid rock). The frost-line number is filled by the jurisdiction in Table R301.2 — use this page's state helper only as a planning override, then confirm with your building department.
When should I buy bagged concrete instead of a ready-mix truck for footings?
As a budgeting tip on this page: under about 1 yd³ bags are often practical for DIY; from about 1–3 yd³ compare both (short-load fees matter); above about 3 yd³ a truck usually wins. Local pricing decides.
What is the difference between a strip footing and a pad footing on this calculator?
Strip mode sizes one continuous rectangular run (length × width × depth). Pad/pier mode sizes rectangular isolated pads and multiplies by count. Round cardboard forms belong on the Sonotube calculator.
Should I add waste when ordering footing concrete?
Yes — 5–10% is standard practice for trench unevenness, form spread, and chute cling. Running short on a structural pour is worse than leftover concrete.
Is this concrete footing calculator a structural design tool?
No. It estimates volume, bag counts, optional cost, and a stated rebar takeoff. Width, depth, strength, reinforcement schedules, and frost depth follow IRC/ACI, soil data, and a licensed professional.
Planning a separate floor-preparation pour? Use the self-leveling concrete calculator for underlayment quantities; footing concrete is a separate estimate. Slab volume: concrete slab calculator. Round piers: sonotube concrete calculator.
Last updated 2026-11-03 · About TrueToolCalc and how we check numbers · Found an error? Use the contact page.